Giant 16.8M BioCap® Digester Cover Installed at West Hornsby WRP

Hydroflux Epco designed, fabricated and assisted with the installation of a larger 16.8M BioCap Digester Cover for the West Hornsby WRP located in Sydney. The equipment was fabricated and installed over 2023/2024.

BioCap® is custom fabricated for new digester builds or it can be easily adapted for retrofit to existing digesters. In many instances the fabrication is a combination of factory and onsite works that is managed by Hydroflux, anywhere in Australia or New Zealand.

The cover was of a fixed design and was installed on the existing anaerobic digesters.  The design included:

  • Mild Steel Painted construction
  • Domed construction to improve structural integrity and eliminate internal truss-based construction.
  • Inspection hatches for top entry monitoring
  • Instrument flanges
  • Pressure and Vacuum Relief Valve Flanges
  • Manholes inclusive of sight ports with wipers for access and visual monitoring of digester internals
  • Perimeter handrail with self-closing gate
ParameterValueUnit
Total Internal Diameter 16.875mm
Total Side Wall Height725mm
MaterialPainted Mild Steel
Gas Holding Capacity (From Top of Wall)279.2m3
Tank Wall Flatness Tolerances+-1-2mm